設備和管線的Hydrostatic and Pneumatic Test 到底有何不同
2019/08/26 21:55
瀏覽1,181
迴響0
推薦0
引用0
設備和管線的Hydrostatic(水壓) and Pneumatic(氣壓) 測試 到底有何不同
以下文章可以看看
https://www.whatispiping.com/pressure-tests-of-piping-systems-hydrotest-vs-pneumatic-test
https://www.araner.com/blog/pressure-test-hydrostatic-pneumatic-requirements/
http://www.rootlaw.com.tw/LawArticle.aspx?LawID=A040290070005200-1030627&ShowType=Ref&FLNO=65000
摘取部分如下
Comparison of Hydrostatic and Pneumatic Testing:
Hydrostatic Testing
|
Pneumatic Testing
|
Test pressure is normally 30% higher than the design pressure
|
Test pressure is normally 10% higher than the design pressure
|
Recommended for high pressure applications
|
Recommended only for low pressure applications
|
Test media (Water) used is not compressible by pressure application
|
Test media (Air) used is compressible by pressure application
|
Energy stored per unit volume of water under test pressure is very negligible
|
Energy stored per unit volume of compressed air under test pressure is very high
|
Needs thorough cleaning after test to
eliminate moisture especially for service which are reactive to moisture / fluids
|
Easy to clean after testing
|
Pressure Relief devices are recommended to control sudden increase in pressure during testing
|
Pressure relief devices are must during test to ensure no over pressurisation
|
Chances of equipment/ Pipe / test apparatus
failures are very low
|
Chances of equipment/ Pipe / test apparatus
failures are high
|
Weight of equipment along with test medium as
water is high hence special attention should be given to floor and supporting arrangements
|
Weight of equipment with test medium
as air is comparatively less
|
Needs verification and examination of joints and connections before testing
|
Needs very careful checking of weld joints thoroughly before testing
|
Test media can be reused or transferred to other place after testing
|
Test media can not be reused or transferred to other place after testing
|
Skilled and semi skilled personnel can carry out the test
|
Needs involvement of senior experienced staff to monitor the test.
|
Recommended where large volumes are to be tested at same time (example pipe lines )
|
If pipe lines are tested should be done with small segmental lengths at a time.
|
Damages made by failures are less compared to failures in pneumatic testing
|
Damages made by failures in testing are very huge and extensive
|
Hydrotest is a regular day to day practice and safe procedure and it can be followed in any work site
|
Needs special attention and safety precautions
|
Pressure changes finite amount by infinitesimal change in volume |
Pressure change proportional to volume change |